Memorial High School project holds line at $224.3 million as working group reviews construction progress.
Memorial High School working group approves zero-net-cost change orders and reviews construction progress. Chair Joseph B. Bertrand presided as the group reviewed a four-week construction schedule across roofing, interior finishes, electrical, and site work trades. Bond Building presented PCO-321
Permanent Building Committee · Meeting of September 10, 2026
WAKEFIELD — Memorial High School working group approves zero-net-cost change orders and reviews construction progress. Chair Joseph B. Bertrand presided as the group reviewed a four-week construction schedule across roofing, interior finishes, electrical, and site work trades.
Bond Building presented PCO-321 for Landrigan Field turf replacement totaling $745,018 but offset entirely by contingency reduction. The project remains on track for substantial completion February 27, 2028, with the original contract value holding at $224,337,256. The working group also finalized site logistics for January 2026 school opening, including temporary bus drop-off on Hemlock Road, police traffic detail, and accessibility accommodations, while approving design details for a new gymnasium court and commemorative plaques honoring The Savings Bank's role in the former high school's performing arts program.
In the full story:
- The complete report — 367 words
Source: the Permanent Building Committee meeting of September 10, 2026, compiled from the official minutes.
Members read the rest of this story and every Wakefield meeting we cover, in full.
Become a memberAlready a member? Sign inA 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms
Share this brief
Know someone in Wakefield who follows town government? Share Townbrief Wakefield: they can sign up free.